Typical Layout of Six PC Production Lines

Double wall circulation systems 4+1

Precast concrete planks Land demand:

Total area: about 100,000 square meters

Building area of workshop: 25,000 square meters

Component stack area: 50,000-60,000 square meters

Other: office buildings, dormitory buildings, etc.

Composition of plank:

The standardized workshop is a 5-span steel structure workshop (the best span is 200 m * long and 27 m wide).

It consists of a double-skin wall automation production line + an exterior wall panel automation production line + an interior wall panel, a laminated panel automation production line + a stationary precast production line and a steel bar process production line. Annual design capacity is 300,000 cubic meters.

Precast concrete types:

Plate components: including all kinds of precast panels such as exterior wall panels, interior wall panels, composite floor panels, air conditioning panels, etc.

Special-shaped components: PCF panels, stairs, balconies, floating windows, beams and columns

Plant construction cycle:

The total project period is 8-10 months (including 90 days of production line installation)